Contract award · 11 Apr 2024

Keadby 132kV Substation

Northern Powergrid awarded “Keadby 132kV Substation” to an unnamed supplier on 11 Apr 2024.

Construction workNorth East

Value Not published
WinnersNot named

Open competition

Open procedure: the contract was advertised and any supplier could submit a bid.

Key facts

Suppliers
Not named
Value
Not published
Procedure
Open procedure
Sector
Construction work · Substation construction work (CPV 45232220)
Timeline
  1. Contract date11 Apr 2024
  2. Published5 Jun 2024Published 55 days after the contract date

Description

Phased construction of new elevated GIS and control room building on piled foundations with raised steel stairs and landings and structure bases on piled foundations, together with access roads, palisade fencing, electric fencing, underground drainage, underground ducting and draw pits, modifications to existing Telecoms room and associated site works.

Other awards in the same procurement

Call-offs and awards published under the same process (for example a framework or dynamic purchasing system).

More from Northern Powergrid

All contracts

Recent construction work contracts

Sector overview