Contract award · 2 Sep 2024

RS - Madeira Terraces Restoration Phase 1 - Main Contractor

Brighton & Hove City Council awarded “RS - Madeira Terraces Restoration Phase 1 - Main Contractor” to JT Mackley & Co Ltd for £12.5m on 2 Sep 2024.

Construction workSouth East

Value £12.5m
WinnerJT Mackley & Co Ltd SME

Competition with a shortlist

Competitive procedure with a selection stage: suppliers were shortlisted before being invited to bid.

Key facts

Buyer
Brighton & Hove City Council · Regional or local authority
Value
£12,500,000
Procedure
Restricted procedure
Sector
Construction work · Construction work (CPV 45000000)
Timeline
  1. Contract date2 Sep 2024
  2. Published2 Sep 2024Published the same day

Description

The restricted tender process intially decsribed a scope of 40 arches, associated deck, retaining wall repairs and delivery of a new lift. The shortlisting exercise at SQ returned 4 successfully shortlisted bidders. Due to inflation the scope of the project was reduced to 28 arches, associated deck, retaining wall repairs and delivery of a new lift. The award of the contract resulted in some value engineering from the original scope which slightly altered methodology and consolidated some smaller areas of work such as planters on the decking. Additional information: The restricted tender process intially decsribed a scope of 40 arches, associated deck, retaining wall repairs and delivery of a new lift. The shortlisting exercise at SQ returned 4 successfully shortlisted bidders. Due to inflation the scope of the project was reduced to 28 arches, associated deck, retaining wall repairs and delivery of a new lift. The award of the contract resulted in some value engineering from the orig…