Contract award · 18 Jul 2025

CO Construction - 132/275kv Substation works ECI - Clash Gour WF - 0625

Scottish Hydro Electric Transmission plc awarded “CO Construction - 132/275kv Substation works ECI - Clash Gour WF…” to an unnamed supplier on 18 Jul 2025.

Construction workScotland

Value Not published
WinnersNot named

Competition with a shortlist

Competitive procedure with a selection stage: suppliers were shortlisted before being invited to bid.

Key facts

Suppliers
Not named
Value
Not published
Procedure
Negotiated procedure with prior call for competition
Sector
Construction work · Substation construction work (CPV 45232220)
Region
Scotland
Timeline
  1. Contract date18 Jul 2025
  2. Published22 Jul 2025Published 4 days after the contract date

Description

The works are the Early Contractor Involvement and associated design, engineering and pre-construction and associated works / services

Other awards in the same procurement

Call-offs and awards published under the same process (for example a framework or dynamic purchasing system).

More from Scottish Hydro Electric Transmission plc

All contracts

Recent construction work contracts

Sector overview