Contract award · 13 Aug 2025

Traction Power & Earthing Upgrades - Phase 1 Works

Transport for Greater Manchester awarded “Traction Power & Earthing Upgrades - Phase 1 Works” to Siemens Mobility Limited for £527k on 13 Aug 2025.

Construction workNorth West

Open competition

Open procedure: the contract was advertised and any supplier could submit a bid.

Key facts

Buyer
Transport for Greater Manchester · Body governed by public law
Value
£527,457
Procedure
Open procedure
Sector
Construction work · Construction work (CPV 45000000)
Timeline
  1. Contract date13 Aug 2025
  2. Published26 Aug 2025Published 13 days after the contract date

Description

TfGM has established a contract to ascertain current asset condition information & outline design (Phase 1). At present there are a number of assets (exact extents unknown) which are located within the OCLZ within 1CC that were not electrically bonded when the system was “floated” in 2017. All existing 1CC line-side assets, that fall within the OCLZ, must be assessed against relevant standards and the Metrolink Infrastructure Technical Specification System Earthing Policy to ensure compliance and any identified non-compliances rectified on site.

About the supplier

More from Transport for Greater Manchester

All contracts

More won by Siemens Mobility Limited

All contracts

Recent construction work contracts

Sector overview