Contract award · 28 Apr 2025

621600 - Western IC entry slip road pavement - construction phase support

National Highways awarded “Western IC entry slip road pavement - construction phase support” to DSD Construction Ltd for £231k on 28 Apr 2025.

Construction workWest Midlands

Value £231k
WinnerDSD Construction Ltd SME

Competition with a shortlist

Competitive procedure with a selection stage: suppliers were shortlisted before being invited to bid.

Key facts

Buyer
National Highways · Body governed by public law
Value
£231,185.88
Procedure
Call-off from a framework agreement
Sector
Construction work · Surface work for highways (CPV 45233210)
Timeline
  1. Contract date28 Apr 2025
  2. Published16 Oct 2025Published 171 days after the contract date

Description

A63 Western IC EB Entry Slip Road - 2000A63/443 (0.755km long) This is a single lane slip road which leads off the A15 SB. Records indicate this slip road was resurfaced in 2016 with some previous deeper targeted inlays completed in 2008. The current defects include surface course deterioration, joint deterioration and cracking. Some defects are present in the local authority owned section, 10m prior to the start of the slip road - the scheme has been extended to incorporate these defects. There are currently no concerns with regards to texture however, between Ch.0m and 150m SCRIM is as low as -.005. There are two isolated areas of rutting at 11.5mm and TSD Cat 3 has been recorded between Ch.0m and 150m. Deflectograph data is not currently available. Wholescale inlays of 90mm deep are proposed for the entire length of the slip road. This approach acknowledges the core findings and Cat 3 TSD readings however, there are no significant structural failures and this depth is deemed approp…