University of Chester Decarbonisation of Wheeler & Queens Park ITT, using CCS Framework RM6314 - Demand Management & Renewables Framework - Lot 3.2: Heat Pumps - Projects £1m and above

University of Chester awarded “University of Chester Decarbonisation of Wheeler & Queens Park ITT…” to Dalkia Energy Services Ltd for £4.4m on 19 Dec 2025.

Fuel & energyNorth West

Value £4.4m

Competition with a shortlist

Competitive procedure with a selection stage: suppliers were shortlisted before being invited to bid.

Key facts

Value
£4,400,000
Procedure
Call-off from a framework agreement
Sector
Fuel & energy · Petroleum products, fuel, electricity and other sources of energy (CPV 09000000)
Timeline
  1. Contract date19 Dec 2025
  2. Published16 Jan 2026Published 28 days after the contract date

Description

In March 2025, University of Chester was awarded funding through the Government's Public Sector Decarbonisation Scheme (PSDS), administered by Salix Finance. The funding supports a decarbonisation programme (including the University's contribution) to be delivered between April 2025 and March 2028 across the Wheeler Campus and Queens Park Campus. The project includes the replacement of end-of-life gas boilers with heat pump technology, installation of rooftop solar photovoltaic panels, and associated energy efficiency improvements. This further competition was for a Pre-Construction Services Agreement (PCSA) for the design stage, which, upon agreement, will then progress to the build phase. Following a further competition the University of Chester has issued an Intention to Award to Dalkia Energy Services Ltd under the CCS Framework RM6314 - Demand Management & Renewables Framework, Lot 3.2: Heat Pumps - Projects £1m and above. The design phase is due to be completed by March 2026 in …