Awarded without open competition. The buyer went directly to one or a few suppliers instead of advertising the contract. Procurement rules allow this only in specific cases, such as extreme urgency, when only one supplier can do the work, or for call-offs from an existing framework.
Key facts
- Buyer
- West Midlands Combined Authority · Regional or local authority
- Supplier
- Haigh Rail Limited SME
- Value
- £135,448.37
- Procedure
- Award procedure without prior publication of a call for competition
- Sector
- Construction work · Track construction works (CPV 45234116)
- Region
- West Midlands
- Official notice
- 081054-2026 on Find a Tender
- Timeline
-
- Contract date31 Jul 2026
- Published26 Aug 2026Published 26 days after the contract date
Description
Provision of Priestfield Mitigations LC084 - Phase 2- Transition Renewal Works for Midland Metro Limited (MML). The following activities will be required throughout this work package: 1. Review of current on-site stored ballast levels 2. Full removal of contaminated ballast to geotextile level 3. Replacement of ballast including alignment 4. Drainage survey and cleaning 5. Drainage Design